U-18-036(2)/U-18-051(2)

ORDER SCHEDULING HEARING

Type Procedural
Effective Date 8/17/2018
Tracking Number 18-0242
Related Entities Chugach
Related Matters
U-18-036 In the Matter of the Petition Filed by CHUGACH ELECTRIC ASSOCIATION, INC., Holder of Certificate of Public Convenience and Necessity No. 8, to Create a Regulatory Asset to Amortize Cooper Lake Power Plant Dredging Costs
U-18-051 In the Matter of the Petition Filed by CHUGACH ELECTRIC ASSOCIATION, INC., Holder of Certificate of Public Convenience and Necessity No. 8, to Create a Regulatory Asset to Amortize Beluga Power Plant Unit No. 3 Overhaul Costs
To sort by a column, click the column heading Total Results: 1
 File NameDescriptionFile SizeFile Type 
u18036.2.pdf Order 112619 kb .pdf